A resource and technology model for construction in three days: a KT workshop

Kontur Technologies held a closed practical workshop for a regional developer preparing to scale residential construction across several cities. In three intensive days, using the customer’s materials, the team created a construction resource and technology model, a BIM model with an intermediate level of detail, and a schedule based on the technological sequence of work.

Workshop: The team works with drawings, a BIM model and a construction schedule on a three-panel video wall.
Client
Regional developer
The challenge
Prepare a model to scale construction
Three-day result
Resource and technology model, BIM model and construction schedule

The client’s challenge

An actual project as the basis for working together

The customer is developing a gated residential complex of 12 apartment buildings with restrained Northern European architecture. The workshop used the design documentation and cost estimates for a residential building. The aim was to create a model the team could develop and use when preparing subsequent projects.

We worked with the original drawings, specifications and estimate line items. This enabled discussion of specific structural elements, quantities and construction arrangements directly with the customer’s team.

Construction model

Building → structural elements → activities → resources

KT organised the data into a consistent structure: the residential building, its structural elements, the work required and the resources needed to carry it out. Physical quantities, units of measurement and prices were specified for work and materials. The resource and technology model connects the building’s components to what is needed to construct them.

The model included price changes by period over a multi-year horizon and integration with FGIS CS, the federal construction pricing information system. Published prices for the relevant periods and assumptions about future trends are considered separately. Changes in resource costs can therefore be included in planning while keeping the calculation basis clear.

The structure of the resource and technology model
Isometric section of an apartment building: frame and slabs, wall construction, finished facade and construction materials
01/Object

Building

Multi-unit
residential building
02 / Structural elements

Building components

Foundation, frame,
slabs, walls
03 / Work

Building walls

Work in technological
sequence
04/Resources

Work resources

Materials, labour, machinery

Resources required for the work

Materials

Wall materials, masonry mortar, reinforcement and ties specified in the design

m³ · t · pcs

Labour

Workers and equipment operators

staff-hours

Equipment

Material handling and mechanisation

machine-hours
Physical quantitiesUnits of measurementPrices by periodFGIS CS

Data verification

Check the data first

Preparing the model involved comparing cost estimates with design documentation: checking physical quantities, units of measurement and the scope of work. Correct arithmetic in the totals does not by itself establish that the model is consistent. Discrepancies become visible when individual items are checked against drawings and specifications.

The working materials separately addressed errors in transferring units of measurement, conformity of materials to the design, and completeness of the work included. Confirmed discrepancies were distinguished from questions requiring clarification by the designer. Making source data suitable for management decisions is an important part of KT’s work.

BIM, schedule and 1C

BIM model, Spider Project and 1C integration

During the intensive workshop, we built a BIM model with an intermediate level of detail and developed a construction schedule in Spider Project. Site preparation, earthworks, substructure works, floor-by-floor frame construction, building envelope, engineering systems, finishing and landscaping were placed in the overall construction sequence.

The work included integration with 1C. We considered the project structure, resource data and scheduling together with the customer’s accounting environment. This provides a foundation for linking the construction plan to actual operations.

The result was a completed schedule and a working model for further refinement and use. The customer’s expansion plans define the next step: adapting this foundation for other residential buildings and sites, taking their design and construction conditions into account.

Residential building components with a highlighted wall construction area
BIM

Model with an intermediate level of detail

Structural elements and design decisions

Spider Project

Construction schedule

Work in technological sequence

1C

Customer’s accounting environment

Project structure and resource data

Income and expense budgets and cash flow budgets from KT budgeting projects

Applying AI

AI in engineering tasks

AI technologies were used to process and structure data, analyse drawings, detect clashes and automate routine operations. AI helped connect information from different documents and identify areas requiring verification.

The team checked the results against the source materials. A possible contradiction identified by AI was examined by engineers; once verified, the data was used in the resource and technology model and schedule. The value lies in processing large volumes of information faster while retaining control over the result.

AI analysis and engineering verification
Isometric sequence: source drawings and cost estimates, document comparison using AI, and an engineer checking the data against source materials before it is used in the model and schedule.
Source materials
Source materials

Drawings, specifications, cost estimates

Processing and analysis
Processing and analysis

AI

Team verification
Team verification

Data for the model and schedule

How KT works

Think. Design. Build.

Think.

We examine the challenge of scaling construction, the quality of source data and the questions the model must answer: what is being built, which work and resources are needed, how they are distributed over time and what affects cost.

Design.

We connect design documentation, the work structure, resource calculations, BIM, Spider Project and 1C. We define where AI fits into the work and how its results will be checked.

Build.

Together with the customer’s team, we assemble a model of the actual building, check the data and develop the schedule. In three days, participants gained a practical result and experience with tools they can use in their own projects.

Working together

Developing solutions through closed workshops

KT holds closed practical workshops with clients using their tasks and materials. We share experience in designing and applying technology, while the customer’s team contributes knowledge of its industry, processes and constraints.

Joint work helps test new tools in practice and define subsequent tasks more precisely. The client sees the possibilities in a familiar project; KT receives feedback that informs the development of solutions and working methods. The intensive workshop produced a model, a schedule and a team ready to continue working with modern tools.